Construction Updates.
2025

February
February saw the start of drywalling in the lobby area as well as testing of our innovate automated parking system, and saw the commissioning of fan coil units and mechanical equipment begin.

January
The start of 2025 has been very busy on site. Installation of appliances have begun, and framing/drywalling of corridor and ceilings continues. We are working to complete remaining masonry work on the South Elevation of the building.
2024

December
To close out 2024, the Hoist successfully came down, a major milestone for the project. The migration to permanent mechanical and electrical services is underway.

November
The interior work has commenced on the lower floors including tile, Hardwood flooring, and kitchen installation. We have begun waterproofing the loading dock area as well as begun the framing of amenity areas on the ground level.

October
During the month of October we completed the brick cladding along the East elevation. Balcony Railing installation has begun, as well as the drywalling and mudding of suites on the Third/Fourth floor.

September
September was another busy month. The elevator cabs are underway, interior suite mechanical and electrical is underway, as well as exterior terrace pavers.

August
The end of summer brought great progress on the site. The masonry work was completed on the South – West corner, our team began interior suite framing, and waterproofing was completed on the terraces.

July
July was another busy month on Site. The Crane came down which is an important milestone for the project. The brick cladding has begun on South side. Interior framing started, as well as the process to waterproof the rooftop.

June
June saw great progress throughout the month. We now have heavy gauge studs/sheathing progressing up to 11th Floor. Windows are installed up to the 6th floor, and waterproofing has commenced on the main floor.

May
May was a milestone month on the site. The building main Roof slab has been poured and the top is now officially on the building. Window installation began and is continuing smoothly.
.jpg)
April
During the month of April, the 10th floor concrete slab was completed, the exterior sheathing & studs for 3rd and 4th Floor were installed, and work continues in the parking level to install the parking system.

March
The continued warm weather in March was ideal for continued concrete pours throughout the month. The concrete slabs are now up to the 9th floor. Drywall has begun in the basement level and painting/installing light fixtures in the Automated Parking System has commenced.

February
The balmy weather during the month of February allowed for great progress with concrete pours. The 6th floor concrete slab and verticals as well as the 7th floor slab deck were completed. The service connections (domestic and fire water line, storm line) were also completed.

January
During the month of January, concrete work continued and 4th floor concrete slab and verticals are now 100% complete. Plumbing piping work began on the 2nd floor, and the lateral connections to the heritage façade were also completed.
2023

December
December was a busy month on site. The 3rd floor slab and verticals were completed and work on the 4th floor deck began. The lateral support for the heritage façade is ongoing. The Mechanical and Electrical sleeving for slab and walls also continued to progress.

November
During the month of November the site was busy pouring concrete. To date, the 2nd floor is 100% complete and the 3rd floor formwork has started. The heritage retention & reshoring work for the ground and 2nd floors are now complete. Toronto Hydro civil work has also been completed.

October
In the month of October, the ground floor slab was completed. The walls and columns of ground to the second floor are 90% complete, and the re-shoring of the heritage façade from P1 to ground was also completed.

September
September was a busy month at the site. The underground drain work has been completed, as well as the slab on grade in P1. The ground floor deck installation has begun, and rebar and carpentry work on ground floor started. Heritage Restoration along Yonge St was also started.

August
In the month of August the site was busy with activity. Excavation and Backfill of the P1 level at Automated Parking has been ongoing. All Shotcrete walls are complete and underground drain installation, as well as waterproofing of foundation walls are ongoing. Preparing rebar and for Slab on Grade Pour.

July
July activity included the install of sump pits, elevator walls poured for P1 to ground level, and footings and walls completed FTG 1-5.

June
We had a busy month of June. The crane was erected on the site, which is a large milestone in the construction process. As well, dewatering and soil removal has been ongoing.

May
In the month of May the shoring was demobilized from site. Demoltion along the TTC Demolishing wall is underway. Dewatering work begun for the crane pad, and Excavation and pouring the crane pad and elevator shaft was performed.

April
In April work continued with bulk excavation, lagging, soil testing and erecting the safety hoarding along the TTC tracks.
.png)
March
Excavation and lagging ongoing along Yonge Street. Connecting temporary power is underway. Drilling and installing of wooding posts for TTC hoarding underway.

February
Tie backs have been installed and testing has begun. The site is ready for bulk excavation.

January
Vertical drilling has been completed. The heritage façade retention with needle beams is now 90% completed. The excavation for test tie back has been completed. The temporary power shack has been installed.
2022

December
Demolition has been completed. Backfilling has been completed from the basement up to ground floor level The Drill rig platform has been prepared. The Heritage façade winter protection construction is complete.

November
Demolition of back side of building completed. Backfilling has been completed. Drill Rig platform is ongoing. Drill rig is on site and drilling of piles starts December 1, 2022.

October
The Heritage façade retention is completed. Building demolition, site cleaning and debris removal is ongoing.

September
Abatement work completed. Internal retention for heritage façade completed. Heritage Brick and stone salvaging completed. Demolition started at the Southwest units .
.jpeg)
August
Interior Demolition and abatement has been completed. Interior Demising Walls have been braced with steel channels. Demolition/Retention/Conditional Shoring permits have been issued. Existing Heritage Brick removal ongoing. Brick shall be re-used at a later date during Heritage Restoration phase of the project.

July
Update Interior demolition is now complete. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

June
All existing site services (gas, hydro, water, sanitary) have been disconnected. Interior demolition currently ongoing. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

May
The pedestrian walkway has been constructed.