Construction Updates.

2023
Image
March

Excavation and lagging ongoing along Yonge Street. Connecting temporary power is underway. Drilling and installing of wooding posts for TTC hoarding underway.

Image
February

Tie backs have been installed and testing has begun. The site is ready for bulk excavation.

Image
January

Vertical drilling has been completed. The heritage façade retention with needle beams is now 90% completed. The excavation for test tie back has been completed. The temporary power shack has been installed.

2022
Image
December

Demolition has been completed. Backfilling has been completed from the basement up to ground floor level The Drill rig platform has been prepared. The Heritage façade winter protection construction is complete.

Image
November

Demolition of back side of building completed. Backfilling has been completed. Drill Rig platform is ongoing. Drill rig is on site and drilling of piles starts December 1, 2022.

Image
October

The Heritage façade retention is completed. Building demolition, site cleaning and debris removal is ongoing.

Image
September

Abatement work completed. Internal retention for heritage façade completed. Heritage Brick and stone salvaging completed. Demolition started at the Southwest units .

Image
August

Interior Demolition and abatement has been completed. Interior Demising Walls have been braced with steel channels. Demolition/Retention/Conditional Shoring permits have been issued. Existing Heritage Brick removal ongoing. Brick shall be re-used at a later date during Heritage Restoration phase of the project.

Image
July

Update Interior demolition is now complete. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

Image
June

All existing site services (gas, hydro, water, sanitary) have been disconnected. Interior demolition currently ongoing. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

Image
May

The pedestrian walkway has been constructed.