Construction Updates.

2024
Image
February

The balmy weather during the month of February allowed for great progress with concrete pours. The 6th floor concrete slab and verticals as well as the 7th floor slab deck were completed. The service connections (domestic and fire water line, storm line) were also completed.

Image
January

During the month of January, concrete work continued and 4th floor concrete slab and verticals are now 100% complete. Plumbing piping work began on the 2nd floor, and the lateral connections to the heritage façade were also completed.

2023
Image
December

December was a busy month on site. The 3rd floor slab and verticals were completed and work on the 4th floor deck began. The lateral support for the heritage façade is ongoing. The Mechanical and Electrical sleeving for slab and walls also continued to progress.

Image
November

During the month of November the site was busy pouring concrete. To date, the 2nd floor is 100% complete and the 3rd floor formwork has started. The heritage retention & reshoring work for the ground and 2nd floors are now complete. Toronto Hydro civil work has also been completed.

Image
October

In the month of October, the ground floor slab was completed. The walls and columns of ground to the second floor are 90% complete, and the re-shoring of the heritage façade from P1 to ground was also completed.

Image
September

September was a busy month at the site. The underground drain work has been completed, as well as the slab on grade in P1. The ground floor deck installation has begun, and rebar and carpentry work on ground floor started. Heritage Restoration along Yonge St was also started.

Image
August

In the month of August the site was busy with activity. Excavation and Backfill of the P1 level at Automated Parking has been ongoing. All Shotcrete walls are complete and underground drain installation, as well as waterproofing of foundation walls are ongoing. Preparing rebar and for Slab on Grade Pour.

Image
July

July activity included the install of sump pits, elevator walls poured for P1 to ground level, and footings and walls completed FTG 1-5.

Image
June

We had a busy month of June. The crane was erected on the site, which is a large milestone in the construction process. As well, dewatering and soil removal has been ongoing.

Image
May

In the month of May the shoring was demobilized from site. Demoltion along the TTC Demolishing wall is underway. Dewatering work begun for the crane pad, and Excavation and pouring the crane pad and elevator shaft was performed.

Image
April

In April work continued with bulk excavation, lagging, soil testing and erecting the safety hoarding along the TTC tracks.

Image
March

Excavation and lagging ongoing along Yonge Street. Connecting temporary power is underway. Drilling and installing of wooding posts for TTC hoarding underway.

Image
February

Tie backs have been installed and testing has begun. The site is ready for bulk excavation.

Image
January

Vertical drilling has been completed. The heritage façade retention with needle beams is now 90% completed. The excavation for test tie back has been completed. The temporary power shack has been installed.

2022
Image
December

Demolition has been completed. Backfilling has been completed from the basement up to ground floor level The Drill rig platform has been prepared. The Heritage façade winter protection construction is complete.

Image
November

Demolition of back side of building completed. Backfilling has been completed. Drill Rig platform is ongoing. Drill rig is on site and drilling of piles starts December 1, 2022.

Image
October

The Heritage façade retention is completed. Building demolition, site cleaning and debris removal is ongoing.

Image
September

Abatement work completed. Internal retention for heritage façade completed. Heritage Brick and stone salvaging completed. Demolition started at the Southwest units .

Image
August

Interior Demolition and abatement has been completed. Interior Demising Walls have been braced with steel channels. Demolition/Retention/Conditional Shoring permits have been issued. Existing Heritage Brick removal ongoing. Brick shall be re-used at a later date during Heritage Restoration phase of the project.

Image
July

Update Interior demolition is now complete. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

Image
June

All existing site services (gas, hydro, water, sanitary) have been disconnected. Interior demolition currently ongoing. Overhead protection of Yonge Street and over head protection on Manor Road at the bridge have been erected. Structural demolition and shoring to begin shortly.

Image
May

The pedestrian walkway has been constructed.